Feed-in tariff 2026: rates for every period and your blended rate

For systems commissioned from 1 August 2026 to 31 December 2026, the grid operator pays 7.70 ct/kWh for surplus power up to 10 kWp and 12.22 ct/kWh for full feed-in, for 20 years.

Checked by Radif Partners · Editorial policy · How we calculate

Feed-in

near Stuttgart

Smart meter fitted?

Feed-in tariff

7.53 ct/kWh

€856 a year for 11,371 kWh

Surplus feed-in, rates in ct/kWh
up to 10 kW7.70 ct
over 10 to 40 kW6.66 ct
over 40 to 100 kW5.44 ct
Blended rate for 12.0 kWp7.53 ct
fed in per year11,371 kWh
Payment per year€856
over 20 years€17,117
Step-by-step calculation
  1. What counts is the commissioning date: 1 August 2026 to 31 December 2026. The rate applies for 20 years plus the commissioning year.
  2. Above 10 kWp the rate is blended: the first 10 kW at the first rate, the rest at the second (section 48(2) EEG).
  3. Only the surplus is fed in: 85 % of output at 4,000 kWh consumption.

Estimate based on average weather 2005 to 2023 (PVGIS) and metered household loads. A single year can differ by a few per cent. How we calculate

The German feed-in tariff (Einspeisevergütung) under the EEG 2023 depends on the commissioning date and then stays fixed for 20 years. The Federal Network Agency publishes the rates for each period; since February 2024 they have fallen by 1 % every six months. If you connect between 1 August 2026 and 31 December 2026, surplus feed-in earns 7.70 ct/kWh for the share of capacity up to 10 kW, 6.66 ct/kWh for the part up to 40 kW and 5.44 ct/kWh up to 100 kW. For full feed-in the rates are 12.22 ct/kWh and 10.24 ct/kWh. Larger systems receive a blended rate, which is 7.53 ct/kWh for a 12 kWp system. In the Stuttgart example, with 4,000 kWh of consumption, that system exports 11,371 kWh and receives €856 a year. The EEG 2023 covers systems commissioned up to 31 December 2026; for later systems there is so far only a draft bill.

Rates for every period since 2023

Feed-in tariff in ct/kWh for systems on buildings, per capacity share, according to the Federal Network Agency.
CommissionedSurplus to 10 kWSurplus to 40 kWSurplus to 100 kWFull to 10 kWFull to 40 kWFull to 100 kW
1 August 2026 to 31 December 20267.706.665.4412.2210.2410.24
1 February 2026 to 31 July 20267.786.735.5012.3410.3510.35
1 August 2025 to 31 January 20267.866.805.5612.4710.4510.45
1 February 2025 to 31 July 20257.946.885.6212.6010.5610.56
1 August 2024 to 31 January 20258.036.955.6812.7310.6810.68
1 February 2024 to 31 July 20248.117.035.7412.8710.7910.79
1 January 2023 to 31 January 20248.207.105.8013.0010.9010.90

The figures come from the publications of the Federal Network Agency, earlier periods from its archive. Surplus feed-in (Teileinspeisung) means the household uses power first and only the surplus is paid for (section 21 EEG). With full feed-in (Volleinspeisung) all power goes to the grid, and the rate is higher (section 48(2a) EEG). All rates in the table are already 0.4 ct per kWh below the reference value (anzulegender Wert), as section 53(1) EEG provides for the feed-in tariff.

How the blended rate works

The capacity thresholds are not steps above which the whole system gets less. Each share of capacity is valued at its own rate, and the average applies to every kilowatt-hour exported.

Blended rate for commissioning from 1 August 2026.
SystemSurplus feed-inFull feed-in
10 kWp7.70 ct/kWh12.22 ct/kWh
12 kWp7.53 ct/kWh11.89 ct/kWh
15 kWp7.35 ct/kWh11.56 ct/kWh
25 kWp7.08 ct/kWh11.03 ct/kWh
40 kWp6.92 ct/kWh10.74 ct/kWh
60 kWp6.43 ct/kWh10.57 ct/kWh
100 kWp6.03 ct/kWh10.44 ct/kWh

A 25 kWp system thus reaches 7.08 ct/kWh, a 60 kWp system 6.43 ct/kWh. The calculator above forms this blended rate for any capacity and period and, using the yield for your postcode, works out how much arrives each year.

What reduces the annual payment

Two rules of the solar peak law affect systems from 25 February 2025. Without a smart meter they may export only 60 % of their capacity (section 9(2) EEG); with one, no payment is made while the wholesale price is negative (section 51 EEG). The calculator applies one or the other depending on your choice. The reduction of 1 % per half-year is set by section 49 EEG; it only affects new systems. More under solar peak law and negative power prices.

What is planned from 2027

All rates on this page apply under the EEG 2023 to systems commissioned up to 31 December 2026. For later systems the federal government has tabled a draft bill that would replace the fixed payment for new systems with a time-limited transitional payment. It has not been passed. What it would mean for a system is compared under feed-in tariff 2027. If you are torn between surplus and full feed-in, see full or surplus feed-in.

Questions readers ask

Which feed-in rate applies to a system connected in November 2026?

The rate for the period from 1 August 2026 to 31 December 2026: 7.70 ct/kWh up to 10 kWp for surplus feed-in, 12.22 ct/kWh for full feed-in. What counts is the commissioning date, not the purchase contract or the registration. The rate then applies for the commissioning year and 20 further calendar years (section 25 EEG).

What is the blended feed-in rate for a 12 kWp system?

7.53 ct/kWh for surplus feed-in with commissioning from 1 August 2026. The first 10 kW are valued at 7.70 ct/kWh, the remaining 2 kW at 6.66 ct/kWh, weighted by capacity (section 48(2) EEG). For full feed-in the same calculation gives 11.89 ct/kWh. The rate therefore depends on installed capacity, not on how much is actually exported.

Does full feed-in pay with 12 kWp and 4,000 kWh of consumption?

In the Stuttgart example, narrowly yes: full feed-in brings €1,525 a year, surplus feed-in €1,459 from payment plus the saved electricity bill. At 8 kWp, surplus feed-in is ahead (€1,045 against €1,112). Choosing full feed-in requires notice to the grid operator before commissioning, and you can switch each year before 1 December (section 48(2a) EEG).

How much tariff does a smart meter cost at negative prices?

With a smart meter, no payment is made in quarter-hours with a negative wholesale price (section 51 EEG). For 12 kWp in Stuttgart that comes to about €214 a year, based on the share of negative hours in SMARD data. Without a smart meter the 60 per cent cap applies instead, costing 403 kWh here. Part of the lost time is added at the end of the payment period.

How far has the rate up to 10 kWp fallen since 2023?

From 8.20 ct/kWh in the period from 1 January 2023 to 7.70 ct/kWh from 1 August 2026, a drop of 6.1 %. The rate stayed unchanged until January 2024 and has since been reduced by 1 % every six months (section 49 EEG). Anyone who connected earlier keeps their old rate for the full term.

Keep calculating

Laws and data

Written by

Publisher of German solar calculators: yield by postcode, self-consumption, feed-in tariff

Updated on · Editorial policy · Contact

Rates 2026, read on